As part of the Beachfill Nourishment Project, crews are planting dune grass and placing 8,000 linear feet of sand fencing in Rehoboth Beach. The dune crossover work has been completed that included pedestrian, vehicular and ADA access. The dune grass planting and fence installation is expected to be...
The final phase of the $11.2 million Beachfill Nourishment Project for Rehoboth Beach and Dewey Beach, the extension of two stormwater outfall pipes at Virginia and Maryland Avenues, began March 6. Great Lakes Dredge & Dock Company has been hired for the outfall repair work and is starting equipment...
On Monday, March 13, weather permitting, the road will be closed from 7 a.m. to 4 p.m. to thru traffic from Bayard Avenue to King Charles Avenue on the second block of Hickman Street. During this time the water service will be turned off and on for replacement of a water main. Street access is...
The sidewalk area in front of new City Hall on the north side of Rehoboth Avenue will be temporarily closed for project construction. The sidewalk will be closed Monday through Friday, 8:00 a.m. to 5:00 p.m., from March 13 through the end of April. If the contractor is doing overhead work on a...
Equipment mobilized March 6 and work is underway today to remove trees that uprooted a stormwater manhole site at the corner of 6th Street and Canal Street. This work will correct the issues with the storm drain system and damage to the canal bank along Canal Street. The intersection of 6th Street...
On March 6, 2017, the Rehoboth Beach Commissioners unanimously awarded bids for Phase 1 improvements to the Wastewater Treatment Plant (WWTP). These improvements are urgently needed due to a biologicial upset at the WWTP exacerbated by mechanical malfunction of equipment at the plant in July 2016...
Thank you for your patience while the Water Department temporarily turned off the water for emergency maintenance from 5th Street to Grove Avenue. The water service has been restored.
During the past eight years, wave action has caused damage to the outfalls at Maryland and Virginia Avenues. As part of the Beachfill Nourishment Project for Rehoboth Beach and Dewey Beach, the U.S. Army Corps of Engineers contract with Great Lakes Dredge & Dock Company calls for the extension of...
Work will commence Monday, March 6, 2017, to remove trees that uprooted a stormwater manhole site at the corner of 6th Street and Canal Street. This work will correct the issues with the storm drain system and damage to the canal bank along Canal Street. This work will require the closure of the...